PRESENTATION
THANK YOU MR CHAIRMAN MY NAME IS xxxxxxxxxxx AND I AM CURRENTLY WORKING WITH xxxxxxxxxxx. THE PROJECT I WOULD LIKE TO PRESENT TO YOU WAS A SUBJECT OF A BUILDING INSURANCE CLAIM.
PERMISSION HAS BEEN SOUGHT FROM THE EMPLOYER TO USE THE INFORMATION. I WOULD ASK THE PANEL TO RESPECT THE EMPLOYER'S REQUEST FOR THE ANALYSIS TO BE USED ONLY FOR THE PURPOSE OF MY ASSESSMENT.
THE PROJECT CONSISTS OF DEMOLITION AND RECONSTRUCTION WORKS TO TWO PRIVATE SEMI-DETACHED OWNER-OCCUPIED BUNGALOWS BUILT AROUND 1960 AND LOCATED AT xxxxxxxxxxxxxxxxxxxx.
I HAVE CHOSEN TO PRESENT THIS PROJECT BECAUSE OF MY EXTENSIVE INVOLVEMENT WITH IT FROM INCEPTION TO COMPLETION. THE PROJECT WAS A VERY GOOD VEHICLE TO DEMONSTRATE MY SKILLS IN NEGOTIATION, COST PLANNING AND COST CONTROL. THE CONTRACTUAL AND OTHER ISSUES RAISED DURING THE COURSE OF THE PROJECT SERVED TO BOTH SUPPLEMENT AND EXPAND MY OWN EXPERIENCE OF QUANTITY SURVEYING PRACTICE.
IN VIEW OF THE TIME CONTRAINTS MY PRESENTATION WILL DEAL WITH ONE OF THE FOUR KEY ISSUES OUTLINED IN MY CRITICAL ANALYSIS REPORT. I HOPE TO DEMONSTRATE MY ABLITY TO COMMUNICATE EFFECTIVELY WHILE WORKING WITH OTHER PEOPLE AND SHOW YOU THAT I HAVE THE TECHNICAL SKILL AND PROFESSIONAL COMPETENCE REQUIRED BY THE PROFESSIONAL BODY.
PHOTOGRAPH ON FLIP CHART THROUHOUT THE INTRODUCTION
MAIN BODY
KEY ISSUES list these on the next chart and when you read through them tell us briefly why each one was key . this is important to remind us of the big picture.
THE KEY ISSUES WHICH I DEALT WITH IN MY CRITICAL ANALYSIS ARE:
1. TIME
2. COST CERTAINTY
3. APPOINTMENT OF THE MAIN CONTRACTOR
4. APPOINTMENT OF SUBCONTRACTOR
THE KEY ISSUE I AM GOING TO DEAL WITH IN DETAIL IS THE TIME.
PRIOR TO MY INVOLVEMENT THE PROJECT HAD BEEN TENDERED FOR AND A CONTRCTOR HAD BEEN APPOINTED. IT SUBSEQUENTLY TURNED OUT THAT THE APPOINTED CONTRACTOR COULD NOT SUPPLY SATISFACTORY CONSTRUCTION PHASE HEALTH & SAFETY PLAN, THEREFORE HIS APPOINTMENT WAS TERMINATED. Comment- tell us briefly why the contractor let this contract go after going to the trouble and expense of tendering just for the want of a h&s plan
Also make sure you are fully aware of the contractual basis for determination and appointment of new contractor
IT WAS AT THIS STAGE THAT I WAS INVOLVED AND WAS GIVEN THE INSTRUCTION TO APPOINT A SUITABLE CONTRACTOR WITHIN FIVE WEEKS OF THE INSTRUCTION.
New flip chart
THE FACT THAT THE BUILDINGS WOULD BE DEMOLISHED MADE IT APPARENT THAT AN ALTERNATIVE ARRANGEMENT HAD TO BE MADE TO ACCOMMODATE THE POLICYHOLDERS TEMPORARILY ELSEWHERE FOR THE DURATION OF THE CONTRACT AND THE PAYMENT FOR THE ALTERNATIVE ACCOMMODATION WOULD BE MADE BY THE INSURER. THAT MEANT THAT TIME OVERRUN ON THE PROJECT WOULD INCREASE THE COST OF ALTERNATIVE ACCOMMODATION THEREBY INCREASING THE TOTAL COST SPENT ON THE CLAIM AS A WHOLE.
CHOOSING THE CORRECT PROCUREMENT STRATEGY IS A KEY TO MEETING PROJECT OBJECTIVES. I REALISED THAT VARIOUS CONTRACT STRATEGIES WILL DELIVER PROJECT OBJECTIVES IN DIFFERENT WAYS. THEREFORE, IN ORDER TO ADDRESS THE TIME RELATED KEY ISSUE ON THE PROJECT, I KNEW THAT CHOOSING THE
THE MAIN PROCUREMENT STRATEGIES WHICH I CONSIDERED WERE AS FOLLOWS;
· A COST REIMBURSEMENT CONTRACT,
· TRADITIONAL LUMP SUM CONTRACT, AND
· NEGOTIATED CONTRACT.
A COST REIMBURSEMENT CONTRACTS WAS REJECTED BECAUSE THE COST OF THE WORK CAN
TRADITIONAL LUMP SUM CONTRACTS - THIS ALLOWS A CONTRACT SUM TO BE DETERMINED
NEGOTIATED CONTRACT - THIS METHOD OF CONTRACTOR SELECTION INVOLVES THE
AGREEMENT OF A TENDER SUM WITH A SINGLE CONTRACTING ORGANISATION. ONCE THE
THIS PROCUREMENT STRATEGY WAS CHOSEN BECAUSE IT WAS MORE LIKELY TO ACHIEVE THE PROJECT OBJECTIVES THAN THE OTHER OPTIONS ALREADY CONSIDERED. THIS WAS BECAUSE IT SATISFIED THE FUNDER'S NEEDS BEST IN TERMS OF TIME AND COST CERTAINTY AND IT WAS THE ONLY PROCUREMENT STRATEGY WHICH ALLOWED EARLY START ON SITE.
It would be good if you could also give some comment on the relative typical costs of a negotiated project for the same work at competitive tender. It would only be your professional opinion but then again that is what we want to know about. On balance I think we can assume that the negotiated price would be more expensive ( how much -as the assessor will probably ask you? ) but of course your point will be that this will be saved in decanting costs plus the benefits to the insurance company of having ‘happy customers’
HAVING DECIDED ON THE
THE MAIN CONTRACTOR OFFERED TO CARRY OUT THE WORKS FOR THE SUM OF £245,430.00. I CONSIDERED THAT THE MAIN CONTRACTOR HAD OVERSTATED THE CONTRACT, AS HIS ESTIMATE WAS 16.5% MORE THAN MY PRE CONTRACT ESTIMATE. Briefly tell us a little about this, based figures on what? Office database or external sources, did you use I.T? THIS NOW FORMED THE BASIS OF OUR NEGOTIATION MEETING, WHICH WAS HELD ONE WEEK AFTER THE ESTIMATE WAS RECEIVED.
DURING THE MEETING, IT WAS ESTABLISHED THAT THE CONTRACTOR HAD ALLOWED VARYING PERCENTAGES FOR ATTENDANCE ON SUBCONTRACTORS, THIS RANGED FROM 50 - 60%. IT AFFECTED THE FOLLOWING ITEMS;
· DEMOLITIONS,
· PILING/FOUNDATIONS
· FIRST FIX M&E
· SECOND FIX M&E
THE CONTRACTOR'S ARGUMENT FOR THE HIGHER PERCENTAGE FOR ATTENDANCE ON SUBCONTRACTORS WAS THAT THEY HAD NO ENOUGH TIME TO PREPARE THE ESTIMATE AND OBTAINED COMPETITIVE TENDER FROM SUBCONTRACTOR FURTHERMORE THEY COULD SEE THE RISK OF RUNNING THE PROJECT AT A LOSS IF CARE WAS NOT TAKEN. I REFERRED THE CONTRACTOR BACK TO SOME OF THE PROJECT HE HAD EXECUTED FOR MY EMPLOYER IN THE PAST, WHICH ONLY ALLOWED 15% UPLIFT FOR ATTENDANCE ON SUBCONTRACTOR. THE CONTRACTOR AGREED TO STICK WITH 15% UPLIFT AS AGAINST THE 50% HE QUOTED.
THE NEXT ITEM TO BE CONSIDERED WAS BRICKWORK, THIS INCLUDED ALL NECESSARY INSULATION. PRIOR TO THE MEETING I HAD A DISCUSSION WITH THE DESIGN TEAM TO SEE IF THE SPECIFICATION FOR INTERNAL BRICKWORK COULD BE CHANGED TO THERMAL BLOCKS, AS THIS WOULD CONSTITUTE A SAVING ON INSULATION. THE POSSIBILITY WAS CHECKED AND THIS WAS PRESENTED TO THE CONTRACTOR AND REDUCED THE CONTRACTOR'S ESTIMATE FROM £31,230.00 TO £26,130.00
CONSIDERATION WAS GIVEN TO THE AMOUNT ALLOCATED FOR PRELIMINARIES WITHIN THE CONTRACTOR'S ESTIMATE. A SUM OF £947.96/WEEK WAS ALLOCATED, THIS WAS CONSIDERED EXCESSIVE. I ASKED THE CONTRACTOR TO ITEMISE ALL THE PRELIMINARY WORKS HE HAD INCLUDED IN HIS ESTIMATE, WE JOINTLY PRICED THIS UP AND CAME TO AN AGREED COST OF £670.71/WEEK.
THE LAST ITEMS FOR CONSIDERATION WERE PROVISIONAL SUMS ON BATHROOM, KITCHEN AND FIRE & SURROUND. BEARING IN MIND THAT IT WAS AN INSURANCE CLAIM AND THE POLICYHOLDER SHOULD BE PUT BACK IN THE SAME FINANCIAL POSITION HE HAD BEEN PRIOR TO THE DAMAGE, THEREFORE THE INSURER WAS NOT LIABLE TO RENEW THE KITCHEN, BATHROOM OR FIREPLACE. THEREFORE THE EXISTING UNITS SHOULD BE CAREFULLY REMOVED, STORED AND REFITTED.
AT THE END OF THE MEETING THE CONTRACT SUM WAS AGREED IN THE SUM OF £205,000.00 THIS INCLUDED £6,000.00 FOR CONTINGENCY.
This section is very good and again could be enhanced by use of flip chart showing how you built up the negotiated savings to bring the cost in to line with your estimate
MY CLOSE INVOLVEMENT WITH THE CLIENT GAVE ME AN INSIGHT INTO AN
OWNER-OCCUPIER'S PRIORITIES ON A PROJECT. I LEARNED THAT LISTENING TO THE CLIENT
INCREASED THE CONTRACT DURATION BY SIX WEEKS, THE VARIATIONS TO THE CONTRACT
MY ESTIMATING AND IT SKILLS HAVE BEEN ENHANCED AS A RESULT OF MY INVOLVEMENT IN
CARRIED OUT FLOOD REINSTATEMENT FOR US IN
THE OUTCOME OF THIS PROJECT HAVE SHOWED ME THAT WHILE A SITUATION MAY SEEM
THANK YOU FOR YOUR TIME - I WILL NOW BE HAPPY TO TAKE ANY QUESTIONS YOU MAY HAVE.
No comments:
Post a Comment